Work Breakdown Structure (WBS) is used in three types of
Estimation:
1.
Estimation using Work Breakdown Structure
2.
Three Point Estimation
3.
PERT
The Project Management Body of Knowledge (PMBOK) defines the
Work Breakdown Structure as a "deliverable oriented Hierarchical
Decomposition of the Work to be executed by the Project Team." WBS is
usually derived with the participation of the entire team and is based on the
team’s collective experience.
WBS can be used to arrive at the effort estimates for the
project. WBS is also used in the estimation methods – Three Point Estimation
and PERT. I have seen that some confusion exists regarding Three Point
Estimation and PERT and they are used interchangeably. However, the two
techniques are different.
Estimation using
Work Breakdown Structure (WBS)
In this estimation method, the system is broken based on the
activities in the system. The activities are further broken into tasks. Based
on the tasks, effort and schedule are estimated.
Normally, Wideband Delphi method is used for arriving at the
effort estimate of the tasks. One can use Three Point Estimation method also
for the effort estimate.
Three Point Estimation and PERT
Three Point Estimation and PERT are based
on three values for each task –
- a most optimistic estimate (O)
- a most likely estimate (M)
- a pessimistic estimate (Least likely estimate (L))
Three Point Estimation
Three Point Estimate (E) is based on the Simple Average and
follows Triangular Distribution.
E = (O+M+L)/3
As you are aware, in a Triangular Distribution,
Mean = (O+M+L)/3
Three Point Estimation is typically used for small
repetitive projects.
PERT (Project Evaluation and Review Technique)
In this method, the most-likely
estimate (M) is weighted 4 times more than the other two estimates (optimistic
(O) and pessimistic (L)). Thus, PERT Estimate (E) is a weighted average and
follows Beta Distribution.
E = (O+4*M+L)/6
PERT is commonly used along with CPM
(Critical Path Method). CPM highlights the tasks that
are critical to the project. If there is a delay in these tasks, the project gets
delayed.
PERT is classically used for large non-repetitive projects,
usually R&D projects.
No comments:
Post a Comment